This blog began in late 2006 with the planning and preparation for a circumnavigation of the world in my 39-foot sail boat Pachuca. It then covered a successful 5-year circumnavigation that ended in April 2013. The blog now covers life with Pachuca back home in Australia.

Pachuca

Pachuca
Pachuca in Port Angeles, WA USA

Sunday, December 23, 2018

Fuel Gauge Working

We had problems with the fuel gauge.

I filled the fuel tank, noting the reading of the fuel gauge at every 20 liters.  The filler overflowed at an unexpectedly low 125 liters yet the gauge remained stuck at one half tank.  I retrieved the instructions from my garage over the weekend and last Monday Greg Hansen used the instructions to verify that the gauge was working correctly and the sender in the tank had an electrical resistance consistent with a half full tank, so the problem was definitely in the sender.
Fuel Sender

Bruce and I removed the sender and found things that I didn't like.  I wasn't too happy with the design of the sender, with the float at the end of a long thin stainless steel arm which I considered susceptible to metal fatigue in a rolling sea where the fuel would be sloshing from side to side.  The holes for fixing the sender onto the tank had been drilled so far from the center that they broke the perimeter of the plate,which didn't look right to me.  The drill holes in the tank were very poorly centered and finally, screws of two different lengths had been used to fix the sender to the tank, something that I considered sloppy and amateurish.  (I purchased a new set of screws.)

After measuring the length of the float arm we concluded that it was hitting the side of the tank and attempted to rotate the sender 180 degrees but we found to our surprise that the mounting holes would not align properly.  At that point we gave up and telephoned the Rob of Sheet Metal Fabrications for help, and to his credited he visited the boat the next morning.

Holes drilled at the perimeter of sender flange
Tank holes off center
Rob assured us that the design of the sender was the standard one that he installed on most boats without ever having experienced a failure.  The drill holes around the mounting plate of the sender were as delivered by the manufacturer.  But he did concede that the holes in the tank could have been better centered.



Success!

He attempted to install the sender 180 degrees from the original as we had tried but ran into the same problem of hole alignment.  He then nipped about 10mm from the length of the float arm and fit the sender in its original orientation.  To our disappointment the sender still reported 1/2 tank so he removed the sender and saw that the wiring which was now excessively long after having cut down the unit to fit my tank was tangled around the float arm.  He tied off the excess wire with a plastic tie and installed the float with no further difficulty.  The excess wiring had  been the problem all along and had cost Bruce and me hours of work, not to mention the visit from the the installer

Re finishing the shower duck board
My homework for last weekend had been to clean, sand, and re varnish the shower recess duck board with Everdure 2-part epoxy wood primer from International Paints.  Belt sanding the outside of the piece was easy, but the120 internal holes were a big problem and I had to be satisfied with a good clean out. of those holes with no sanding.  I hung the piece in the carport and laid down two coats in the holes, four coats underneath, and five coats on the walking surface.  This was a relatively fast process because Everdure can be laid down "wet on wet" with as little as 6 minutes between coats.

I also spent about 8 hours over two days painting the bilge.

By the end of the week I had laid down the required two coats on most of the bilge until I had run out of paint. Bruce painted the rest of the bilge on the following Monday morning. That would put us in position for plumbing the water tanks and finally, after months of accident prone walking along the bilge, re installing the cabin flooring.   The section of the bilge forward of the bulkhead was painted with Hempel 1-part Multicoat Primer/Topcoat, an excellent product that is sadly no longer available.  For the main part of the bilge I used 1-part "Bilgekote" by International Paints.
Bilge Painted

We also put one of the powder-coated toe rails on the deck to see how the color would blend in with the rest of the boat.  I had chosen the color with the intention of changing the deck color from light blue to more of a beige color.  From the top of the boat that would look very good but after considering the color from the perspective of a side view of the boat I agreed that it would be best to retain the light blue deck color.  Fortunately the toe rails will look OK, partly because they will blend in with the generous amount of teak on the deck.
Toe Rail color check

Toe rail at port gunwale

Monday, December 17, 2018

Engine Ready etc

It was a week of slower pace because Bruce was tied up for several days attending to a catamaran in urgent need of attention and I used my time doing small but useful jobs.

I started the week by installing the boat's gas cylinders.  Dominic had told me that rigid straps must be used because the elastic ones were illegal so I used a rigid strap as required, although I will later add elastic straps as a backup.
Gas cylinders in position

I then did a lot of painting.  Painting the section behind the mast was a must-do project because once the mast is back in place access to that area for painting will be impossible. After considering the use of one-part enamel paint I decided keep using 2-part paint because it is so much  stronger and durable than the easier to use 1-part paint, and once I laid a coat of 1-part it would be very difficult to go back to 2-part.

Then there was the inevitable mission creep.  I took Bruce's advice to paint the entire bulkhead rather than just the section behind the mast. Then there was the opportunity to fill in the many holes around the solar and wind controllers aft then paint that bulkhead.  After laying down the second coat of paint I had a lot of the expensive mix remaining so I hurriedly emptied, sanded, and cleaned one of the galley shelf compartments then laid its first coat of paint.  By the end of the week the mast and controller bulkheads as well as the two galley storage compartments had been painted with two coats.
Newly painted galley shelf compartments

For the record  I used: Northane 2-pack linear polyurethane paint, with 5% Northane brush thinner added.  I laid the bulk of the paint down with mohair rollers, 100 mm long with 5 mm naps and used throw-away brushes to trim along the edges.  It all worked very well.

Greg the marine electrician visited on Friday and we discussed the problem of the fuel gauge reporting 1/2 tank full when it is in fact full to the brim.  Either the sender has not been installed properly or, more likely, the gauge has not been calibrated.  We could not find the instructions in the boat so my task this weekend is to find the document in my crammed and disorderly garage.  Greg also took away the new LED light in the steerage compartment that failed after only a few hours of use.
Newly painted cabin bulkhead

Aft bulkhead repaired and painted
Muffler

Mark the mechanic also showed up.  His brief was to connect the engine exhaust hose to the recently repaired muffler (aka "pong box") then bleed the fuel system.  He used some sort of vacuum tool to speed the bleeding process, then the engine burst into smooth life on the first crank.  That was remarkable given that it had been idle with empty fuel lines for about 6 months.  The engine is in superb condition partly because I have been fastidious about maintaining it.  My big fault has been to not use it enough -  only 550 hours in 7 years.  In future I will push aside my purist aversion to motoring when there is any useful wind available and use the iron sail more, while proclaiming loudly that I am doing it for the sake of the engine.

Friday, December 7, 2018

Diesel, LPG, Lettering, Cockpit Drains

I arrived Monday morning to find gentle winds from the NE, ideal putting the new lettering on the hull.  I left a message for Nathan at Go Graphics and one of his people arrived an hour later and did a splendid job in remarkably short time.
New lettering


Dominic of Full on Gas visited and finished the task  of replacing the boat's LPG gas lines. He mounted the selector switch, reduction valve and solenoid assembly on top of the cylinder case (built of 18 mm marine ply and very strong) where the holes and bolts were already in position, then connected the new lines then checked the entire system for leaks using an LPG tank borrowed from Bruce.  (There were no leaks.)   He finished off by making sure that the stove and gas detector were working OK then officially certified the system on line.  Although the gas system had never failed me, we reckoned that the lines were originals from 1983 and it was time to change them.

One of the requirements from Dominic was that the ancient and badly scratched acrylic companionway sliding door be replaced with one that had ventilation holes.  Bruce took the old door to a business that made a beautiful replacement from polycarbonate rather than acrylic, with holes drilled at an angle so that rain would not pass through.   The view from inside of the boat through that new door was amazing and Bruce put the idea into my head of replacing all of Pachuca's windows with polycarbonate.  Looking through the existing windows is like looking through severe cataracts must be.  Yes, they are great for privacy, but wouldn't it be nice to look at the ocean going by from inside the cabin.
New polycarbonate doorway

Great view to the outside

By then Bruce had noticed something disturbing: the thru-hull fittings for the  cockpit drains were both loose: we could rotate them very easily by hand.  Bruce noted that the fittings were hard against the fiberglass hull on the inside rather than  on backing plats, and he reckoned that the fittings no longer had adequate caulking.  This was serious and had to be rectified, and I thanked  Bruce for pointing out the problem.

We enlisted the help of the mechanic from M and J engineering who had arrived to align the boat's propeller shaft and Bruce telephoned Zelko to fabricate the wooden backing plates.  The clamps and hoses were removed with little trouble, as were the elbows and ball valves.  However, removing the thru-hull fittings was very difficult, primarily the port one which had a hopelessly frozen nut and had to be removed from the outside.
Zelko doing a spell at the flange

Backing plates prepared by Zelko on short notice

Beautiful 316 stainless steel

Thru hull fittings in place

That required patient work with an angle grinder to make small cuts in the outer flange to yield small wedges which could then be lifted with a hammer and screwdriver, all without damaging the GRP hull.

By the end of the day the thru hull fittings were in position, with the use of Sikaflex 291 as a bedding compound and on the threads.  A small amount 2-part "Mapoxy" was used on the port side as bedding to repair minor scratches left on the gel coat as a result of removing the old fitting.  Bruce was unexpectedly tied up with another problem on the next day, Friday, and we expect to attach the elbows, ball valves, and hoses on Monday.

While doing this work Bruce noticed that the inlet to the muffler ("pong box") had a crack that had been repaired sort of by someone probably in the USA and he sent it out for repair. 

I occupied my time on Friday painting two bulkheads with Northane 2-part linear polyurethane paint, with 5% Northane brushing thinner.

Now that I have the  "feel" of 2-part painting again I hope to paint the galley shelves and other areas whenever I get spare time.


Saturday, December 1, 2018

Fuel Lines and Bow Rollers

We connected the diesel fuel lines.  The work was difficult because the fuel inlet and breather hose connections are next to each other on the port side coaming, meaning that we had to work on our backs with one arm extended up the narrow cavity of the coaming.  The work spanned two days but in the end I was satisfied with the special hose sealant that Bruce had provided at some effort and the tightness of all of the clamps.
New fuel filler line in position

I found it impossible to route the stiff and heavily ribbed fuel hose through its original path with its tight bends in constricted spaces and suggested that we cut a new hole in the lazarette.  I am glad that we did that because I could then see how the incoming fuel will now had a much smoother path into the tank.

On Monday we will put 30 liters of diesel into the tank and for the first time I will have the pleasure looking at what the new fuel gauge reports.  Then we will contact Mark the diesel mechanic who will return to the boat to bleed the engine and give it a test run which must be short because there will be no cooling sea water.

I picked up the bow rollers and pins from Mirko at "Vision Design" in Bibra Lake on Friday afternoon.  We had dropped them off earlier in the week for more work after we found that the rollers refused to roll because they fit so tightly between the 6mm plates and requested that 2mm be taken from each end of the rollers.  We also needed a way to prevent the pins from falling off the bow fitting and it was agreed that holes would be tapped near the ends of the pins into which retaining grub screws would be fitted after the pins were in position. 
Pins to hold anchor rode on the rollers

I fitted the rollers on the bow and could not believe how easily they turned.   I am looking forward to the prospect of working my anchor rodes  without the extra noise and effort of dragging them over static rollers.

 On Monday we'll fit the pins and if that goes well as expected we'll sign off on the excellent work by Vision Design with both the bow roller system and the binnacle frame.

On Friday I also had a brief visit from Go Graphics sign writing to discuss the replacement of the broad blue line along the outside of the coaming that we had discussed months earlier.  We agreed that it would be a waste of money to replace that line until the entire area was repainted, and I will not have time to do that during this refit.  When the time comes I will contact the firm to coordinate that work with one of my future maintenance haul outs.

The lettering has been prepared and I can  expect it to be laid on the transom in the coming week.

I also expect a visit from Dillon to better align the propeller shaft, which Bruce has deemed too far off centre for safe motoring to Pachuca's pen.

There were also visits from Greg Hansen and Dominic regarding the boat's LPG gas system.

Dominic stripped out the old gas lines, which we agree must have been the originals from 1983.  He looked over my cylinder  housing setup with the reduction valve mounted on top and approved.  He had also instructed that we must have ventilation holes in the sliding companionway "door" and we have ordered a new one made of stronger material and to be tighter fitting, to minimize a gap along the top of the cover which, when one thinks about it, would have provided probably more ventilation that the new door will.  Dominic will return at some indeterminate time to complete the installation of the new lines.

Greg Hansen visited to replace the failing gas sensor in the lazarette then certified the gas detection system.  We tested system by giving each sensor a whiff of methylated spirits.

Saturday, November 24, 2018

Bad Hair Day

Bruce and I are now working off a task list of 33 items, which has been helpful in our scheduling preparatory work.

More work was done on bow roller modification.  Angle plates were welded at the bottom to facilitate the feeding of the chain when weighing anchor.  Lock down pins were fabricated and the fitting of the pins will be completed next week. 
Two of four pin holes have been drilled

No more of anchor chain jumping off roller
The first photo shows the plates that have been welded to the system to keep the chain on the roller and locked down by a pin.

The shaft seal was reinstalled.  The company was able to reface the seal so I was not forced to purchase a new one.  On Friday Bruce re fiberglassed the end of the stern tube and on Monday the seal job will be completed by clamping on the bellows (ie rubber boot).  The mechanic will also re align the propeller shaft which for some reason is out of position.

Contact was made with a gas fitter who will replace the boat's LPG gas lines probably in January.

Now that the transom fittings have been bolted on Bruce has arranged for the boat's stern lettering to be put on in the coming week. 

Bruce and I did a lot of painting during the week.  I spent a difficult 3 hours laying down a coat of enamel paint in the lazarette, which I liken to painting the inside of a coffin with the lid down.  After the cramped work I emerged with my hair covered in lumps of enamel paint, some large, and some small and difficult to see.  I spent the rest of the day looking like Albert Einstein on a bad day and resumed the painting the next day armed with a pair of underpants to protect my hair.  I didn't relish the prospect of being seen wearing a pair of underpants on my head and was fortunately saved by the bag of rags that we had purchased earlier in the week.  One of the rags was large enough to act as a suitable head scarf.

The situation appeared to be so hopeless that I considered shaving my hair.  Fortunately a Google search came up with olive oil as the solution.  On Friday night I cut off about 10 lumps of paint with scissors while watching TV then on Saturday morning I saturated my hair with olive oil to the point where for the next 4 hours I had to have a towel around my neck to manage the oil that was working its way down all around my head.  During these four hours worked at the garage as usual, then when I was ready for a shower I soaked a bit more olive oil into my hair and got to work with a comb. Sometimes I could slide the lumps down with the comb and sometimes I would have to work the lump between my thumb and index finger until it seemed to fall apart.  Twenty minutes later I could pass my comb and hair brush through my hair with no snags and the crisis was over.

Mark the mechanic spent several hours doing maintenance on the engine. The coolant hoses have been replaced with proper ones, the coolant has been replaced,  and the heater has been fitted.  The gear box oil was at the correct level and looked good.  He will return next week to finish his work after Bruce's fiberglass work has set.
Adjustable LED light at top right


I am enclosing a photo of the steerage area with its floor board at LED light at the upper right.

Saturday, November 17, 2018

Binnacle Work Completed


The Cobra steering pedestal came back from the spray painter looking as good as new. 


New Scanstrut instrument pod

Rear View


We then assembled the binnacle on Thursday morning and concluded that the legs of the new stainless steel frame were too short because the instrument pod prevented the full opening of the compass cover and obstructed access to the drinks holder. Greg and I removed the frame without disturbing the steering pedestal or teak wood work then Bruce and I returned the frame that morning with a request that 100 mm be added to the vertical tubes and the slot for the wiring be lengthened by 20 mm.  By noon the next day we had the revised frame on board and Bruce had no trouble sliding the feet through the teak holder.  Greg arrived after lunch and spent the afternoon mounting the instrumentation.

The binnacle work had cost an obscene amount of money and effort but the result was most satisfactory.  We had solved the problem of mounting the Navman GPS onto the instrument pod by having Zelko fabricate and ingenious wooden support that would be screwed onto the surface of the pod.  The photo shows the autopilot panel on the left, the Navman GPS in the centre,  and the anchor windlass switch at the right.  (It was the problem of siting the new windlass switch that had led to the re design of the binnacle in the first place.)  The instruments are now all fully protected from the weather and the cabling is invisible, passing from the inside of the pod pod down the legs of the frame.

During the week Greg also installed a bright adjustable LED light in the steerage section beneath the cockpit, with the switch at the navigation station instrument panel.  What luxury!  A nice piece of flooring too keep me out of the bilge and a bright light to see what I am doing is a far cry from the section being a no-go area protected by a wall of batteries.

My attempt to connect the boat to shore power failed with a light on the new panel indicating incorrect polarity.   Greg took the cable home and swapped the non-standard connector that I had been forced to use with my old boat wiring with a standard (and legal!) one.  And, shame on me, Greg confirmed that I had wired the plug incorrectly with polarity reversed.

Bruce and I re mounted the boat's stainless steel nose plate.  It was a perilous job that could have ended in disaster with the slightest mistake but we managed it with no dramas.  Bruce's wife "Dolphie" had done a marvelous job of treating the metal with Ranex  rust converter then polishing it to a high luster.  It was the original nose plate, which showed the scars of previous battles with anchors, but to me it added character to the piece.
Applying Sikaflex to the bow plate

Plate in position

One day Bruce noticed some deterioration in the rubber boot and clamps around the PYI dripless shaft seal that had installed in Mexico in July 2010. A mechanic was called and removed the unit and noted some pitting on the metal face.  He took shaft seal away either refacing or replacement.  The rubber boot and clamps will be replaced, and Bruce will do some repair on the fiberglass at the end of the stern tube. 

We then had to remove the base upon which the engine covers slides in order that he may sleeve  two holes in the bilge barrier at the  front of the engine compartment.  That led to another day of distraction typical of this project.  We cleaned the oily area below the engine so well that I had to finish the job of removing dry specs of material using a vacuum cleaner.  We then found the beginnings of wood rot in parts of the engine cover assembly so we cleaned, sanded, then treated the wood with several coats of "Awlgrip".  In lifting the base one of the layers acting as a slide for the cover parted and we saw that it had been held together with tiny nails and a layer of Liquid Nails, something totally unsuited for a marine environment but was probably the standard when the boat had been built in 1983.  We put the base back into place, used 2-part "Megapoxy" to re glue the slide, then put the engine cover  back into position to ensure that aligned the track correctly and to apply force to the glued surfaces. 

We had a look at the engine while it was exposed and noted that once again the rack holding the oil filter had become loose with the top bolt loose and the bottom bolt missing altogether.  After some discussion I agreed to bring in an experienced Volvo mechanic that Bruce knew.  The next day the mechanic visited and we had a very productive discussion on the engine and how to manage it.  I have commissioned him to service the engine, which will exclude an oil change which he deemed unnecessary since fewer than 10 hours have been put on the engine since I changed the oil and filter less than a year ago, and the oil looked brand new.  I will also engage him to align the propeller shaft after the boat is back in the water.  One thing that I liked about the man is that he had no hesitation in explaining anything I asked, such as how to change the engine coolant.
Accessible Engine

550 hours of running since installed in Mexico in Jan 2011


Both the mechanics attending to the shaft seal and the engine both marveled at the accessibility of the boat's engine and propeller shaft.




Sunday, November 11, 2018

November Report 2

Pachuca's steering station has two components: the steering pedestal to which is attached the wooden binnacle which supports the compass. 

The Cobra pedestal steering is an all-gear system that is considered to be more reliable than chain or wire systems.  During final preparations for the circumnavigation in 2008 my friend Reg Kelly suggested that we remove it from the boat and have it checked out, and what wise advice that turned out to be.  We managed to remove it and deliver it to a local engineer who took it apart and found it to have a frozen bearing and totally dry of lubrication.  When  I picked it up a grease nipple was pointed out to me but after  the installation of new batteries in New Zealand I very rarely got access to the below-cockpit area for greasing the bearing.
After pedestal removed

Base of pedestal looking very sad

Two weeks ago we removed the unit and found it to appear to be in  bad shape with corrosion starting to eat into the aluminium base.  The bearing  was found to be in bad shape although not corroded, and it appeared that ordinary rather than marine grease had been applied in 2008.  After picking up the refurbished unit we sent it  out for re painting.  The spray painter had done a beautiful job and the unit presented as new. 

By then we had decided have the stainless steel binnacle rebuilt, to be higher and have a bend at the top for better presentation of the instruments.  I agreed mount a Scanstrut instrument pod which would look smart and protect the instruments from the elements.  The pod would also enable us to pass the instrument wiring down the legs of the binnacle rather than down the side as before. We then had difficulty in mounting the stand-alone Garmin 152H GPS which had not been designed for this kind of mounting but we came up with a solution utilizing the woodworking skills of Zelko.

So the instrument pod will accommodate the Garmin GPS in the centre, the Raymarine autopilot head at the left, and the anchor up-down switch at the right.

And last week Bruce and I managed to reinstall the boat's stainless steel bow plate.  The job took a lot of time and patience but fortunately there were no catastrophes.

Saturday, November 10, 2018

November Report 1

Five weeks have passed since my last blog entry.  In this entry I will cover the electrical work of the last few weeks.

Greg Hansen has almost completed what has turned out to be an almost total wiring of the boat which included the following:

1. Re-design of the anchor windlass power system
I had earlier accepted Greg's advice to alter the anchor windlass setup from from supplying electrical power from small battery at the bow that is trickle charged from the house bank to supplying it directly from the engine starter battery via heavy electrical cabling. 

There would be several advantages from the change: (1) Power would now be supplied from a hefty starter battery rather than a smaller AGM battery more suited for supplying steady power rather than starting engines, (2) The cost of the cabling would in the long run pay dividends because there would no longer be the need to replace windlass batteries, (3) Because the windlass would always be worked with the engine running there would be no practical limit on the frequency of anchor lifts whereas the old system had limitations since it relied on a slower trickle charge to replenish the windlass battery, (4) There would be less weight at the bow of the boat, a big benefit to Pachuca with her long and slender bow.
Rewired Windlass


It broke my heart to dismantle the trickle system because it represented a personal triumph of design and implementation.  My brother Arnold, an electrical engineer, supplied the design then Stephen used an amazing on-line simulator to see the behaviour of the circuit using various resistors, diodes, and the relay.  Stephen also provided a large heat sink which nicely took care of heat issues.  But we all agreed that the sacrifice of the good work was justified.

After confirming that the Orca VE 2000 windlass could reverse to drop as well as raise the anchor Greg installed the required wiring which included a heavy breaker at the navigation station.
Windlass Breaker

In future I will be able to raise and lower the anchor from the steering station, yielding great improvements in efficiency and safety.  But that led to the problem of finding space for mounting the new switch at the steering station, which led to a rebuild of the binnacle documented later.

2. Re-wired all of the battery cabling

Two of the house batteries and the starter battery had been re positioned to the starboard quarter berth locker which necessitated a lot of cabling work.  While he was at it Greg replaced the cabling between the two house bank batteries in the cabin.  During this work Greg suggested that we split the four house bank batteries into two separate banks in order to minimize the risk of one bad battery bringing down the entire house bank.  The cabling work included running special wires to the BEP voltage and amperage monitor, which I modified to display voltages for "HOUSE 1", "HOUSE 2", and "STARTER".

3. Replaced all of the internal 12v lighting  

All of the internal lighting is now LED.  Dome lights were installed in the aft bunk area, clothes locker, head, and navigation station.  For the first time I am able to use a red light at the desk when navigating at night.  Large LED lights were installed in the cabin and galley, and new high quality brass lights were installed over the cabin bunks and forward V section bunk.

4. New Switches 

A new switch allows me to direct power from the solar panels and wind charger to either house bank, and another one which allows me to use power from either house bank.  (House Bank 1 is the two batteries aft rated at 480 a/h and House Bank 2 is the two batteries in the cabin, rated at 540 a/h.) Note that the starter battery is charged solely from the engine alternator, and when it reaches full charge a voltage sensitive relay directs the alternator charge to the house bank.
Switch to direct solar and wind power

Switch to select which house bank to use


5. New lighting

Wiring has been set up for new lights at the cockpit and in the space below the cockpit and Greg expects to receive and install the new lights in the coming week.

6. Upgraded the 240V wiring to current standards

 Greg was legally and ethically obliged to upgrade the 240V AC system to current standards and I certainly did not object to that.  He put the heavy cabling in conduit, installed an RCD, and neatened the entire setup.

6. Installed an electrolysis blocker

Electrolysis Blocker
Greg installed an electrolysis blocker which will allow me to connect the boat to shore AC power with no fear of electrolysis due to faulty wiring of the shore power source.


7. Tidied Electrical Panel

Greg did a marvelous job of removing redundant wiring then tidying up the main electrical panel.  He also replaced switches with breakers in a new extension panel that I had installed on the door. I sacrificed the ancient (but working) Lowrance GPS in order to accommodate the panel for the 240V A/C breakers.

I finally have for the first time a very good understanding of the boat's wiring and plan to document it at first opportunity.
New switch panel lower left, A/C breakers at right

Wiring now tidy and and labeled

Thursday, October 4, 2018

Another Month of Progress

I was away for most of the month of September on a 3-week trip to visit family in the USA.  I departed knowing that I was leaving Pachuca in good hands and that Bruce would maintain his usual brisk pace of progress.

The first thing that I noticed on my return was the splendid look of Pachuca's hull now that Bruce had laid 3 of 5 coats of 2-part epoxy primer below the waterline.  Pachuca's sleek lines are striking and I received several compliments from admirers. 
Hull with 3 of 5 layers of  2-part epoxy  primer

Several other less grand but very important tasks had been completed. 

I had managed to circumvent the planet with plastic thru-hull fittings and no shut of valves at the stern and Bruce corrected this.  These outlets were above the waterline in calm water but would have presented a danger in rough seas.

The new fuel gauge had been fitted above the companionway, so that for the first time I would not have to guess how much fuel I had on board.
New Fuel Gauge

The two "Seabird" vents on the cockpit coaming that had caused me so much grief because they could not be blocked off from taking in water during heavy seas had been replaced with vents that could be rotated in any direction and capped off in heavy seas.

The new larger solar powered vent had been fitted above the head.  A larger hole had been cut through the deck and Zelko had fabricated from teak a level base for the vent.

The old-style Whale Gusher manual bilge pump on the starboard side of the cockpit had never worked.  Its role was to pump water out of a dead spot in the bilge below the cockpit.   Consequently that part of the bilge was always full or nearly full of water.  At some difficulty Bruce and Zelko fitted a new all-plastic Whale Gusher  pump to match the one at the rear of the cockpit.  So Pachuca now has two manual and one electric bilge pumps.
View to Foredeck

Solar powered vent

Bruce took delivery of the two new water tanks and new diesel fuel tank. 

The rebuilt rudder arrived at about the time of my return.  Rebuilding the rudder cost approximately $2,900, and this does not include the cost of the hours of labour in dropping and reinstalling the rudder.

I resumed my work of tidying up the electrical breaker panel, steadily removing redundant wiring. One afternoon Bruce gave me a had in pulling out a bundle of redundant wiring running from the lazarette to the main electrical panel.  The wiring was from the SABB diesel engine that I had replaced in Mexico.

One afternoon's worth of redundant wiring
We also spent the better part of 2 days fitting a relatively heavy copper strap between the HF tuner and the Dynaplate strapped to the hull.  This strap was heavy enough to last for many years but was extremely difficult to work into position.

Bruce and I discussed the installation of a light prism in the head and an order has been placed.  These prisms are very effective in gathering external light and directing it into the space below deck.
Zelko fitting batteries

Batteries strapped into position

The rudder was installed on Tuesday.   It took more than an hour of effort to jack the rudder stock into position.  New bushes were  used, which has eliminated a bit of play at the lower end of the rudder.  The packing also new, as would be expected.  I am looking forward to sailing the boat with the rudder contributing buoyancy rather than dragging the stern of the boat down because it is full of water.
New thru-hull fitting and valve.  Note backing plate.



At left is connection of earth strap to HF tuner

This morning Zelko showed up and set up the new bases for the stern batteries that he had fabricated.  One by one the heavy batteries were lifted into position then strapped down with the specially fabricated aluminium frames. Everything had worked out as planned and the result was pleasing in every way: neat, professional, and strong, and.  We figure that those batteries will now remain in place during a rollover. 


Then we installed the new diesel tank that Bruce had been carrying around in his van for about 2 weeks.  Once again everything has gone as planned and the new tank fit nice and snug on strips of rubber that Bruce had glued on the supports.  Zelko will strap the tank down after the tank has been plumbed into the boat's fuel system.  The tank is constructed of 3mm marine grade aluminium.

Greg Hansen the semi retired boat electrical man with whom I've been dealing with since the1980's visited late yesterday and we had a very productive session. 

He will start by cabling the batteries in their new location. 
Then he will also wire up the anchor windlass so that it will have a switch above the steering wheel for both raising and lowering the anchor.  The foot switch at the bow for raising the anchor will remain.  There will also be a switch at the cockpit for deactivating the entire circuit.  In order to accommodate the new windlass switch we will have the welder extend the stainless steel tube frame at the binnacle by 130mm.  While we are at it we will have slots cut into the vertical tubes of the frame so that the binnacle instrument (i.e. compass, autopilot head, GPS, windlass switch) can  pass into the interior of the boat without being seen and with much better protection than having the wires strapped to the legs.  For the first time I will be able to raise and lower the anchor while at the steering station rather than the bow, a great help when sailing solo.  Previously I had to lower the anchor manually at the bow.

Greg will also bring the 240V electrical cabling up to current standard: the cabling will be in conduit, an RCD will be installed at the switch panel, and the switch plywood panel will be replaced with non-combustible material.

Greg will also lead the way in wiring the starboard side of the boat, using the latest techniques for bundling the wiring.

This electrical work represents more mission creep but it represents a major step in making the boat safer and easier to handle.

I finished off the day by discussing with Bruce my selection of new interior lights for the boat.  After some helpful suggestions by Bruce we completed the order list which is going to be a big one: 4 reading lights for the forward and cabin bunks, two dome  lights for the  aft bunks, a dome light for the head, and large  lights for the galley and cabin.  All lights will be LED's
Strap bolted to the Dynaplate

Strap run  to lazarette
New coaming vent (sealed off) and Whale Gusher pump below


Rebuilt rudder in position
Top of diesel tank with inspection plate and fuel sensor at right

Drain will be fitted at the bottom of the tank.



New diesel tank in position

.



Blog Archive

Contributors

Statistics Click Me